Storage Sense

Unit Addition

Fort Myers, FL

We partnered with the Storage Investment Group to deliver their tenth and final building, a 10,000-SF climate-controlled storage facility, through comprehensive preconstruction and construction services.

During preconstruction, our team focused on critical aspects like navigating the confined site and maintaining seamless access to the existing operational complex for storage members. This thorough planning paved the way for efficient construction of the 72-unit building..

Construction workers in yellow safety gear installing a large pipe in a trench, surrounded by tools and equipment.
Excavation site with a large pipe connected to a valve system, surrounded by dirt and gravel, with some greenery at the top and sides.

Case Study

This case study highlights best practices employed during the coordination and installation of a 6" fire-main to ensure a cost-effective, efficient, and successful outcome.

By proactively implementing best practices such as verifying appropriate underground sizing, checking for recirculation issues, coordinating with local jurisdictions on hookup requirements, and strategically routing lines outside of swales to minimize excavation, we work to deliver a cost-effective, efficient, and successful project.